5 skilled workers can build a wall in 20days; 8 semi-skilled workers can build a wall in 25 days; 10 unskilled workers can build a wall in 30 days; If a team has 2 skilled, 6 semi-skilled and 5 unskilled workers, how long will it take to build the wall?
Solution follows here:
(A) 20 days
(B) 18 days
(C) 16 days
(D) 15 daysSolution follows here:
Solution:
5
skilled workers can build a wall in 20days
=> 1
skilled worker can build a wall in 20 * 5 = 100 days
=> 1
skilled worker can complete 1/100 th of work in one day
8 semi-skilled
workers can build a wall in 25days
=> 1
semi-skilled worker can build a wall in 25 * 8 = 200 days
=> 1
semi-skilled worker can complete 1/200 th of work in one day
10 un-skilled
workers can build a wall in 30days
=> 1
un-skilled worker can build a wall in 30 * 10 = 300 days
=> 1
un-skilled worker can complete 1/300 th of work in one day
Given that a team has 2 skilled, 6 semi-skilled and 5
unskilled workers:
2 skilled can
complete 2 * (1/100)th of work in one day => 1/50th
6 semi-skilled
can complete 6 * (1/200)th of work in one day => 3/100th
5 un-skilled can
complete 5 * (1/300)th of work in one day => 1/60th
The team can
complete => 1/50 + 3/100 + 1/60 = (6+9+5)/300
= 20/300 = 1/15th
of work in one day
This means team
can complete the work in 15 days
Answer (D)